What steps are required to create a parallel set of table load operations from already created data flows?
The correct answer is B. Open a control flow and move a parallel process to a blank space in the flow; then drag the. See the full explanation below for the reasoning.
Question
What steps are required to create a parallel set of table load operations from already created data flows?
Options
- AOpen a data flow and move a parallel process to a blank space in the flow; then drag the desired
- BOpen a control flow and move a parallel process to a blank space in the flow; then drag the
- COpen a control flow and place all of the data flows on the canvas; connect the 'success' port of
- DPut all the data flows into one data station and create a control flow.
How the community answered
(62 responses)- A6% (4)
- B76% (47)
- C13% (8)
- D5% (3)
Community Discussion