OG0-093 · Question #295
Which phase of the TOGAF ADM is the first phase directly concerned with the planning for the implementation of the target architecture(s)?
The correct answer is B. Phase E. Phase E (Opportunities & Solutions) is the first phase in the TOGAF ADM directly concerned with planning for the implementation of the target architecture by identifying delivery vehicles and creating an initial implementation plan.
Question
Which phase of the TOGAF ADM is the first phase directly concerned with the planning for the implementation of the target architecture(s)?
Options
- APhase D
- BPhase E
- CPhase F
- DPhase G
- EPhase H
How the community answered
(44 responses)- B93% (41)
- D5% (2)
- E2% (1)
Why each option
Phase E (Opportunities & Solutions) is the first phase in the TOGAF ADM directly concerned with planning for the implementation of the target architecture by identifying delivery vehicles and creating an initial implementation plan.
Phase D (Technology Architecture) focuses on defining the desired technology architecture, not directly on implementation planning.
Phase E, Opportunities & Solutions, is where the implementation approach is determined, and an initial implementation plan is formulated. This phase identifies key opportunities, assesses implementation readiness, and defines projects to deliver the target architecture.
Phase F (Migration Planning) focuses on detailed project-level planning for migration, which follows the initial planning done in Phase E.
Phase G (Implementation Governance) is concerned with overseeing and ensuring adherence to the architecture during actual implementation, not the initial planning.
Phase H (Architecture Change Management) deals with managing changes to the architecture after it has been implemented.
Concept tested: TOGAF ADM Phase E implementation planning
Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap06.html
Topics
Community Discussion
No community discussion yet for this question.