The correct answer is D. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool.. The Consolidated Gaps, Solutions, and Dependencies Matrix is a critical TOGAF deliverable used to document and manage the architectural gaps, proposed solutions, and their interdependencies, serving as a primary planning tool.
Question
Options
- ADetermine the set of Solution Building Blocks required by identifying which Solution Building
- BCreate an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps,
- CGroup the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies
- DUse a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool.
Explanation
The Consolidated Gaps, Solutions, and Dependencies Matrix is a critical TOGAF deliverable used to document and manage the architectural gaps, proposed solutions, and their interdependencies, serving as a primary planning tool.
Common mistakes.
- A. While determining Solution Building Blocks (SBBs) is part of architecture development, this choice doesn't describe the primary purpose of the Consolidated Gaps, Solutions and Dependencies Matrix itself.
- B. Creating an 'Implementation Factor Assessment and Deduction Matrix' is not a standard TOGAF deliverable or term related to the Consolidated Gaps, Solutions and Dependencies Matrix.
- C. Grouping SBBs from the matrix isn't its primary function; rather, the matrix is a tool to manage and plan the solutions themselves, which might involve SBBs.
Concept tested. TOGAF ADM deliverables and planning tools
Reference. https://pubs.opengroup.org/architecture/togaf9-2-doc/arch/chap26.html#tag_26_06_07