nerdexam
ExamsOG0-093Questions#218
The_Open_Group

OG0-093 · Question #218

OG0-093 Question #218: Real Exam Question with Answer & Explanation

The correct answer is D. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool.. The Consolidated Gaps, Solutions, and Dependencies Matrix is a critical TOGAF deliverable used to document and manage the architectural gaps, proposed solutions, and their interdependencies, serving as a primary planning tool.

ADM Phase E: Opportunities & Solutions

Question

Scenario Please read this scenario prior to answering the Question You are serving as the Lead Architect for an enterprise architecture project team within a leading multinational pharmaceutical and medical devices manufacturer. Its brands include numerous household names for medications and first aid supplies. The company has a long history of innovating new treatments for many common illnesses and diseases. Prior to launching a new treatment, the company has to demonstrate Its effectiveness and safety in a set of clinical trials that satisfy the regulatory requirements of the countries in the target markets. All clinical trials are undertaken by its research laboratories, which employ over 10,000 people at separate facilities in the United Kingdom, United States, Sweden, France, Canada, India, China and Japan. In addition to internal research and development activities the company is also involved in publicly funded collaborative research projects, with other industrial and academic partners. The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners. The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their clinical trials. This system will also connect with external partners. The Enterprise Architecture group is a mature organization. They use the TOGAF 9 ADM with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant. The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. She has stated that the changes to the enterprise architecture for the new system will need to be rolled out in stages on a regional basis that minimizes disruptions to ongoing clinical trials. Refer to the Scenario, you have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s). Based on TOGAF, which of the following is the best answer?

Options

  • ADetermine the set of Solution Building Blocks required by identifying which Solution Building
  • BCreate an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps,
  • CGroup the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies
  • DUse a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool.

Explanation

The Consolidated Gaps, Solutions, and Dependencies Matrix is a critical TOGAF deliverable used to document and manage the architectural gaps, proposed solutions, and their interdependencies, serving as a primary planning tool.

Common mistakes.

  • A. While determining Solution Building Blocks (SBBs) is part of architecture development, this choice doesn't describe the primary purpose of the Consolidated Gaps, Solutions and Dependencies Matrix itself.
  • B. Creating an 'Implementation Factor Assessment and Deduction Matrix' is not a standard TOGAF deliverable or term related to the Consolidated Gaps, Solutions and Dependencies Matrix.
  • C. Grouping SBBs from the matrix isn't its primary function; rather, the matrix is a tool to manage and plan the solutions themselves, which might involve SBBs.

Concept tested. TOGAF ADM deliverables and planning tools

Reference. https://pubs.opengroup.org/architecture/togaf9-2-doc/arch/chap26.html#tag_26_06_07

Topics

#Solution Building Blocks#Gaps Analysis#Solutions Planning#TOGAF ADM

Community Discussion

No community discussion yet for this question.

Full OG0-093 Practice