Which one of the following best describes the purpose of ADM Phase E?

The correct answer is A. To define the initial implementation plans. This question asks for the primary purpose of Phase E (Opportunities and Solutions) within the TOGAF Architecture Development Method (ADM).

ADM Phase E: Opportunities & Solutions

Question

Which one of the following best describes the purpose of ADM Phase E?

Options

  • ATo define the initial implementation plans
  • BTo define the scope, identifying stakeholders and obtaining approvals
  • CTo develop the Technology Architecture
  • DTo manage requirements throughout the ADM
  • ETo perform architectural oversight for the implementation

How the community answered

(27 responses)
  • A
    85% (23)
  • B
    4% (1)
  • C
    4% (1)
  • E
    7% (2)

Why each option

This question asks for the primary purpose of Phase E (Opportunities and Solutions) within the TOGAF Architecture Development Method (ADM).

ATo define the initial implementation plansCorrect

ADM Phase E, 'Opportunities and Solutions,' focuses on identifying major implementation projects and defining initial implementation plans. This phase bridges the gap between the architecture definition (Phases B, C, D) and the actual implementation and migration, by evaluating implementation options and formulating a high-level plan.

BTo define the scope, identifying stakeholders and obtaining approvals

Defining the scope, identifying stakeholders, and obtaining approvals are primary activities of the Preliminary Phase and Phase A (Architecture Vision), not Phase E.

CTo develop the Technology Architecture

Developing the Technology Architecture is the primary focus of ADM Phase D (Technology Architecture), not Phase E.

DTo manage requirements throughout the ADM

Managing requirements throughout the ADM is the purpose of the Requirements Management phase, which is an ongoing activity across all ADM phases, not specific to Phase E.

ETo perform architectural oversight for the implementation

Performing architectural oversight for the implementation is an activity typically covered in Phase F (Migration Planning) and Phase G (Implementation Governance), not the core purpose of Phase E.

Concept tested: TOGAF ADM Phase E purpose

Source: https://pubs.opengroup.org/architecture/togaf9-2-doc/arch/chap06.html#tag_06_09

Topics