OG0-093 · Question #262

Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project? ActualTests.com

The correct answer is E. Requirements Management. Requirements Management is a continuous activity within the TOGAF ADM that is revisited throughout the architecture project to manage changes and ensure alignment with stakeholder needs.

ADM Requirements Management

Question

Which phase of the ADM is an on-going activity that is visited throughout a TOGAF architecture project? ActualTests.com

Options

  • AArchitecture Change Management
  • BImplementation governance
  • CMigration planning
  • DPreliminary Phase
  • ERequirements Management

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    6% (1)
  • E
    88% (14)

Why each option

Requirements Management is a continuous activity within the TOGAF ADM that is revisited throughout the architecture project to manage changes and ensure alignment with stakeholder needs.

AArchitecture Change Management

Architecture Change Management is a phase focused on establishing procedures for managing change in the new architecture, typically after it's been implemented, not an ongoing activity during the ADM cycle itself.

BImplementation governance

Implementation Governance focuses on guiding and overseeing the implementation of the architecture, ensuring conformance, which is a specific phase activity, not a pervasive one.

CMigration planning

Migration Planning is a specific phase that develops a detailed plan to transition from the baseline to the target architecture, rather than an ongoing activity throughout the entire ADM.

DPreliminary Phase

The Preliminary Phase sets up the architecture capability and context for the ADM, which is a foundational, initial activity, not one that is continuously revisited throughout the project.

ERequirements ManagementCorrect

Requirements Management is explicitly defined in TOGAF as a central, ongoing activity that manages all architecture requirements throughout the ADM cycle. It ensures that changes to requirements are properly assessed and addressed across all phases, influencing and being influenced by them.

Concept tested: TOGAF ADM ongoing activities

Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap19.html

Topics

#Requirements Management#ADM phases#ongoing activity