OG0-093 · Question #263

Which of the following statements best describes risk management in the ADM?

The correct answer is D. Risk is pervasive in all enterprise architecture activity and should be managed in all phases of the. Risk management is a pervasive and continuous activity that should be integrated and managed across all phases of the TOGAF Architecture Development Method (ADM).

ADM Guidelines and Techniques

Question

Which of the following statements best describes risk management in the ADM?

Options

  • ARisk analysis is best conducted in the Architecture Vision phase so that the risk is eliminated in
  • BRisk analysis should be carried out first in the Migration Planning phase
  • CRisk analysis is outside the scope of enterprise architecture projects
  • DRisk is pervasive in all enterprise architecture activity and should be managed in all phases of the
  • EThe only risks that are within the scope of enterprise architecture are technological risks

How the community answered

(46 responses)
  • B
    2% (1)
  • C
    4% (2)
  • D
    91% (42)
  • E
    2% (1)

Why each option

Risk management is a pervasive and continuous activity that should be integrated and managed across all phases of the TOGAF Architecture Development Method (ADM).

ARisk analysis is best conducted in the Architecture Vision phase so that the risk is eliminated in

While risk identification can begin early, restricting risk analysis primarily to the Architecture Vision phase and aiming for complete elimination is unrealistic and underestimates the continuous nature of risk.

BRisk analysis should be carried out first in the Migration Planning phase

Delaying risk analysis until the Migration Planning phase would be too late, as many critical decisions influencing risk are made in earlier phases of the architecture development.

CRisk analysis is outside the scope of enterprise architecture projects

Risk analysis is a fundamental component of effective enterprise architecture, directly within its scope, as architects must consider threats to the architecture's success and value.

DRisk is pervasive in all enterprise architecture activity and should be managed in all phases of theCorrect

TOGAF emphasizes that risk is inherent in all enterprise architecture activities and, therefore, risk management must be an ongoing, pervasive concern addressed systematically throughout every phase of the ADM cycle. This ensures that potential issues are identified, assessed, and mitigated proactively.

EThe only risks that are within the scope of enterprise architecture are technological risks

Enterprise architecture encompasses business, data, application, and technology domains; therefore, risks extend beyond just technological aspects to include business, organizational, and financial risks.

Concept tested: TOGAF ADM risk management principles

Source: https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap23.html

Topics

#Risk management#ADM#pervasive risk