OG0-093 · Question #5

Complete the sentence. The Requirements Management Phase _____________________.

The correct answer is E. stores requirements and manages their flow into relevant ADM phases. The Requirements Management phase in TOGAF is a continuous process that oversees requirements throughout the Architecture Development Method (ADM) cycle.

ADM Requirements Management

Question

Complete the sentence. The Requirements Management Phase _____________________.

Options

  • Aaddresses and resolves requirements between ADM phases
  • Bis a central process that prioritizes requirements for all ADM phases
  • Cis used to dispose of resolved requirements for all ADM phases
  • Dgenerates new requirements and passes them to all ADM phases
  • Estores requirements and manages their flow into relevant ADM phases

How the community answered

(32 responses)
  • A
    3% (1)
  • C
    6% (2)
  • D
    3% (1)
  • E
    88% (28)

Why each option

The Requirements Management phase in TOGAF is a continuous process that oversees requirements throughout the Architecture Development Method (ADM) cycle.

Aaddresses and resolves requirements between ADM phases

Addressing and resolving requirements occurs within specific ADM phases, not as the primary function of the Requirements Management phase itself, which orchestrates their flow.

Bis a central process that prioritizes requirements for all ADM phases

While prioritization is a component, the phase's scope is broader than just prioritization; it encompasses the entire lifecycle and management of requirements.

Cis used to dispose of resolved requirements for all ADM phases

Disposing of resolved requirements is a specific step, but the phase is about managing the entire lifecycle of requirements, not just their disposal.

Dgenerates new requirements and passes them to all ADM phases

Requirements are generated throughout ADM phases, but the Requirements Management phase's role is to capture and manage these, not primarily to generate them.

Estores requirements and manages their flow into relevant ADM phasesCorrect

The Requirements Management phase is responsible for storing and tracking all architecture requirements and ensuring they are managed and flowed into the appropriate ADM phases for consideration and resolution. This phase acts as a continuous process across the entire ADM.

Concept tested: TOGAF ADM Requirements Management Phase

Source: https://www2.opengroup.org/ogsys/catalog/g183

Topics

#Requirements Management#ADM phases#Requirements flow

Community Discussion

No community discussion yet for this question.