You are preparing to install a new 2-node AFF A250 system at a customer site with an existing cluster that uses NetApp CN1610 cluster interconnect switches. In this scenario, what are two valid…
The correct answer is C. Create a new 2-node switchless cluster. D. Migrate the existing cluster to new switches and add the new nodes. Because AFF A250 not supported with CN1610 switches https://kb.netapp.com/Advice_and_Troubleshooting/Flash_Storage/AFF_Series/Controller_Hardw are_Upgrade%3A_Adding_AFF_A250_nodes_to_existing_cluster_report_HA_interconnect_error s_and_cannot_perform_takeover
Question
You are preparing to install a new 2-node AFF A250 system at a customer site with an existing cluster that uses NetApp CN1610 cluster interconnect switches. In this scenario, what are two valid actions for this installation? (Choose two.)
Options
- AAdd the new nodes to the existing cluster and switches.
- BCreate a new 2-node switched cluster that uses the CN1610 cluster switches.
- CCreate a new 2-node switchless cluster.
- DMigrate the existing cluster to new switches and add the new nodes.
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C85% (22)
Explanation
Because AFF A250 not supported with CN1610 switches https://kb.netapp.com/Advice_and_Troubleshooting/Flash_Storage/AFF_Series/Controller_Hardw are_Upgrade%3A_Adding_AFF_A250_nodes_to_existing_cluster_report_HA_interconnect_error s_and_cannot_perform_takeover