NACE-CIP2-001 · Question #31

You are the NACE Level 2 Inspector with the final responsibility to prepare the final report for a very large structural steel shop project which has gone very well. It is due next week. The work…

The correct answer is B. Plainly state in your report that they are missing. You've hit your limit · resets 5am (America/New_York)

Documentation

Question

You are the NACE Level 2 Inspector with the final responsibility to prepare the final report for a very large structural steel shop project which has gone very well. It is due next week. The work has been ongoing for two years and several NACE Level 1 Inspectors have worked under your supervision throughout the project. You find you are missing one week of daily reports for the night shift from the very beginning of the project and despite your best efforts they are cannot found. You FIRST preferred course of action is to:

Options

  • AUse creative writing to cover over the fact they are missing
  • BPlainly state in your report that they are missing
  • CDo not complete your report until they can be found
  • DRe-create the reports as not much was going on during night shift anyway

How the community answered

(51 responses)
  • A
    18% (9)
  • B
    71% (36)
  • C
    8% (4)
  • D
    4% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#missing inspection records#documentation integrity#ethical reporting#final report