Non-Conformance Reports are designed to:

The correct answer is D. To identify items that do not meet the specification requirements. You've hit your limit · resets 5am (America/New_York)

Documentation

Question

Non-Conformance Reports are designed to:

Options

  • APunish the Contractor for substandard work
  • BElevate the status of the Inspector
  • CAssist the Owner in negotiating credits from the Contractor
  • DTo identify items that do not meet the specification requirements

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    13% (7)
  • C
    8% (4)
  • D
    75% (40)

Explanation