Which statement about a withdrawal Kanban in Microsoft Dynamics AX 2012 is true?

The correct answer is B. A withdrawal Kanban is visible on the Kanban schedule board. See the full explanation below for the reasoning.

Question

Which statement about a withdrawal Kanban in Microsoft Dynamics AX 2012 is true?

Options

  • AA withdrawal Kanban is planned.
  • BA withdrawal Kanban is visible on the Kanban schedule board.
  • CA withdrawal Kanban creates a process activity.
  • DA withdrawal Kanban moves the Kanban of an item between warehouses.

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    82% (27)
  • C
    3% (1)
  • D
    12% (4)