Microsoft
MB6-884 · Question #82
Which statement about a withdrawal Kanban in Microsoft Dynamics AX 2012 is true?
The correct answer is B. A withdrawal Kanban is visible on the Kanban schedule board. See the full explanation below for the reasoning.
Question
Which statement about a withdrawal Kanban in Microsoft Dynamics AX 2012 is true?
Options
- AA withdrawal Kanban is planned.
- BA withdrawal Kanban is visible on the Kanban schedule board.
- CA withdrawal Kanban creates a process activity.
- DA withdrawal Kanban moves the Kanban of an item between warehouses.
How the community answered
(33 responses)- A3% (1)
- B82% (27)
- C3% (1)
- D12% (4)
Community Discussion