MB6-884 · Question #26

Which element defines the Work in Process (W1P) ledger accounts for a Lean manufacturing production flow?

The correct answer is D. Value Stream. See the full explanation below for the reasoning.

Question

Which element defines the Work in Process (W1P) ledger accounts for a Lean manufacturing production flow?

Options

  • Acost group
  • Bcosting version
  • Cproduction group
  • DValue Stream

How the community answered

(33 responses)
  • A
    15% (5)
  • B
    9% (3)
  • C
    3% (1)
  • D
    73% (24)

Community Discussion

No community discussion yet for this question.