Question
You are using automated planning in Microsoft Dynamics AX 2012. You need to limit the number of automatically created scheduled Kanbans. What should you do?
Options
- ASet the Maximum planned jobs value.
- BSelect the Product quantity variance check box and set the Automatic planning quantity
- CSet the Automatic planning quantity value and override the Firming time fence value.
- DSet the Automatic planning quantity and Firming time fence values.