In Microsoft Dynamics AX 2012, a Kanban process job has the status of Planned. You cancel the job. What happens to the cancelled job?
The correct answer is A. The job status changes to Not planned. See the full explanation below for the reasoning.
Question
In Microsoft Dynamics AX 2012, a Kanban process job has the status of Planned. You cancel the job. What happens to the cancelled job?
Options
- AThe job status changes to Not planned.
- BThe job record is automatically removed.
- CThe job type changes to Prepared.
- DThe job type changes to Emptied.
How the community answered
(29 responses)- A79% (23)
- B7% (2)
- C3% (1)
- D10% (3)