Microsoft
MB6-884 · Question #81
You are creating event Kanban rules in Microsoft Dynamics AX 2012. You need to replenish material that is required for a downstream process activity. Which event type should you activate?
The correct answer is A. Kanban line event. See the full explanation below for the reasoning.
Question
You are creating event Kanban rules in Microsoft Dynamics AX 2012. You need to replenish material that is required for a downstream process activity. Which event type should you activate?
Options
- AKanban line event
- Bstock replenishment event
- Csales event
- DBOM line event
How the community answered
(21 responses)- A71% (15)
- B5% (1)
- C14% (3)
- D10% (2)
Community Discussion
No community discussion yet for this question.