MB6-884 · Question #81

You are creating event Kanban rules in Microsoft Dynamics AX 2012. You need to replenish material that is required for a downstream process activity. Which event type should you activate?

The correct answer is A. Kanban line event. See the full explanation below for the reasoning.

Question

You are creating event Kanban rules in Microsoft Dynamics AX 2012. You need to replenish material that is required for a downstream process activity. Which event type should you activate?

Options

  • AKanban line event
  • Bstock replenishment event
  • Csales event
  • DBOM line event

How the community answered

(21 responses)
  • A
    71% (15)
  • B
    5% (1)
  • C
    14% (3)
  • D
    10% (2)