When inventory transactions for completed quantities are processed as financially updated during the backflush costing calculation, which status is the receipt status updated to reflect?

The correct answer is A. Ordered. See the full explanation below for the reasoning.

Question

When inventory transactions for completed quantities are processed as financially updated during the backflush costing calculation, which status is the receipt status updated to reflect?

Options

  • AOrdered
  • BSold
  • CPurchased
  • DReceived

How the community answered

(27 responses)
  • A
    81% (22)
  • B
    7% (2)
  • D
    11% (3)