Microsoft
MB6-884 · Question #19
When creating an event Kanban, which setting links the Kanban rule to the production flow version?
The correct answer is B. Product selection. See the full explanation below for the reasoning.
Question
When creating an event Kanban, which setting links the Kanban rule to the production flow version?
Options
- ALast plan activity
- BProduct selection
- CFirst plan activity
- DReplenishment strategy
How the community answered
(31 responses)- A16% (5)
- B71% (22)
- C3% (1)
- D10% (3)
Community Discussion