MB5-858 · Question #71

You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft Dynamics products for your customers. Your customer's major stakeholders identify significant…

The correct answer is B. Avoid D. Transfer. See the full explanation below for the reasoning.

Question

You are a project manager, and you use Microsoft Dynamics Sure Step for implementations of Microsoft Dynamics products for your customers. Your customer's major stakeholders identify significant changes that will increase the scope of a project. Which two risk response strategies for the project definition update should you use? (Each correct answer presents part of the solution, Choose two.)

Options

  • AExploit
  • BAvoid
  • CEnhance
  • DTransfer
  • Eshare

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    84% (32)
  • C
    3% (1)
  • E
    11% (4)

Community Discussion

No community discussion yet for this question.