You have successfully executed your project and the contract is formally closed. Are there any remaining tasks to complete?

The correct answer is A. Yes. You still need to c communication management. See the full explanation below for the reasoning.

Question

You have successfully executed your project and the contract is formally closed. Are there any remaining tasks to complete?

Options

  • AYes. You still need to c communication management.
  • BYes. You still need to provide post Go-live support and verify the project scope.
  • CNo. After contract closing, there are no remaining tasks.
  • DYes. You still need to implement the minority of changes agreed upon during contract closing.

How the community answered

(29 responses)
  • A
    72% (21)
  • B
    3% (1)
  • C
    14% (4)
  • D
    10% (3)