You are creating a Project Charter. Which information should you include in this document? Choose the 3 that apply.

The correct answer is A. Information about in-scope and out-of-scope areas. B. Project approach and governance that describe the approach, key milestones, timeline, deliverables, D. Business and project objectives that describe the desired output and effect for the customer organization. See the full explanation below for the reasoning.

Question

You are creating a Project Charter. Which information should you include in this document? Choose the 3 that apply.

Options

  • AInformation about in-scope and out-of-scope areas.
  • BProject approach and governance that describe the approach, key milestones, timeline, deliverables,
  • CThe proposed solution and estimated fees that describe what needs to be implemented and the related
  • DBusiness and project objectives that describe the desired output and effect for the customer organization.

How the community answered

(58 responses)
  • A
    79% (46)
  • C
    21% (12)