Your team has gathered relevant project details by means of pre-sales activities and high level requirements gatherings, including workshops, demonstrations, and interview sessions. All relevant…
The correct answer is B. Project Charter. See the full explanation below for the reasoning.
Question
Your team has gathered relevant project details by means of pre-sales activities and high level requirements gatherings, including workshops, demonstrations, and interview sessions. All relevant information was documented through these activities. You need to centralize this information in one document that will be used to authorize the project to start. This document will outline the overall goals and objectives, define the interactions of all project participants, list the approved scope, document assumptions and risks, and provide the high-level project schedule and approach. Which document do you create?
Options
- AFunctional Requirements Document
- BProject Charter
- CFinal Licenses Agreement
- DScoping Assessment Report
How the community answered
(40 responses)- A3% (1)
- B75% (30)
- C8% (3)
- D15% (6)
Community Discussion
No community discussion yet for this question.