MB5-858 · Question #5
You are working as a project manager in a complex blended engagement that includes consultants from several partners and ISVs. Your customers have communicated that reliable and optimized…
The correct answer is B. Execute the activities related to the Optimization Offering, Performance Review, before Go-live in the. See the full explanation below for the reasoning.
Question
You are working as a project manager in a complex blended engagement that includes consultants from several partners and ISVs. Your customers have communicated that reliable and optimized performance is business-critical. You need to ensure that this concern is addressed and that your team understands the performance impact of the solution. What should you do?
Options
- AExecute the activities related to the project management discipline, Risk and Issue Management, as
- BExecute the activities related to the Optimization Offering, Performance Review, before Go-live in the
- CExecute the activities related to the Optimization Offering, Design Review, as soon as the design documents
- DExecute the activities related to Conducting a Production Audit in the deployment phase.
How the community answered
(34 responses)- A3% (1)
- B74% (25)
- C15% (5)
- D9% (3)
Community Discussion
No community discussion yet for this question.