You are planning a meeting at the end of the Analysis phase that highlights the current health of the project, key milestones achieved, key deliverables completed, project level issues and risks…
The correct answer is B. Tollgate Review. See the full explanation below for the reasoning.
Question
You are planning a meeting at the end of the Analysis phase that highlights the current health of the project, key milestones achieved, key deliverables completed, project level issues and risks, and the conditions of satisfaction assessment. This meeting will be the 'sign-off' of the Analysis phase. Which Sure Step document do you prepare for this meeting?
Options
- ALessons Learned
- BTollgate Review
- CProject Status Report
- DProject Charter
How the community answered
(50 responses)- A4% (2)
- B72% (36)
- C16% (8)
- D8% (4)