nerdexam
Microsoft

MB5-858 · Question #38

You are conducting user acceptance tests. The delivered solution, as deployed in the testing environment, meets all the product specifications and is under planned costs. This project also realized…

The correct answer is A. Ask the customer to file a Change request. See the full explanation below for the reasoning.

Question

You are conducting user acceptance tests. The delivered solution, as deployed in the testing environment, meets all the product specifications and is under planned costs. This project also realized a positive time performance. Your customer requests several changes and will not accept the solution unless you make the changes. What should you do?

Options

  • AAsk the customer to file a Change request.
  • BInform your customer that you can only accept the changes if the estimated costs for these changes are
  • CRefuse to implement the changes in this project because you have completed the project.
  • DUpdate the project issue list with these requested changes.

How the community answered

(30 responses)
  • A
    77% (23)
  • B
    3% (1)
  • C
    7% (2)
  • D
    13% (4)

Community Discussion

No community discussion yet for this question.

Full MB5-858 Practice