Which two activities are specific to the agile project type? (Each correct answer presents part of the solution. Choose two.)

The correct answer is A. define solution backlog B. sprint configuration and development. See the full explanation below for the reasoning.

Question

Which two activities are specific to the agile project type? (Each correct answer presents part of the solution. Choose two.)

Options

  • Adefine solution backlog
  • Bsprint configuration and development
  • Cgather development standards
  • Dvalidate design security

How the community answered

(27 responses)
  • A
    78% (21)
  • C
    7% (2)
  • D
    15% (4)