MB5-858 · Question #109

You complete your project planning. You need to continue with the agile preparation stage of the project. Which activity should you do first?

The correct answer is C. Conduct a solutions overview. See the full explanation below for the reasoning.

Question

You complete your project planning. You need to continue with the agile preparation stage of the project. Which activity should you do first?

Options

  • AGather business requirements.
  • BConduct a Fit Gap Analysis.
  • CConduct a solutions overview.
  • DDefine a solution backlog.

How the community answered

(40 responses)
  • A
    10% (4)
  • B
    5% (2)
  • C
    83% (33)
  • D
    3% (1)