MB5-858 · Question #101

Go live is complete, and you are now in the operation phase of the project, Which two activities can be performed in the operations phase? (Each correct answer presents part of the solution. Choose…

The correct answer is A. Document lessons learned. B. Review deliverables against the statement of work (SOW). See the full explanation below for the reasoning.

Question

Go live is complete, and you are now in the operation phase of the project, Which two activities can be performed in the operations phase? (Each correct answer presents part of the solution. Choose two.)

Options

  • ADocument lessons learned.
  • BReview deliverables against the statement of work (SOW).
  • CPerform end-user training.
  • DConduct production audit.

How the community answered

(19 responses)
  • A
    79% (15)
  • C
    5% (1)
  • D
    16% (3)