Which two components are critical to the success of user acceptance testing? (Each correct answer presents part of the solution. Choose two.)
The correct answer is A. the completion of the end user training C. the usage of user acceptance test scripts. See the full explanation below for the reasoning.
Question
Which two components are critical to the success of user acceptance testing? (Each correct answer presents part of the solution. Choose two.)
Options
- Athe completion of the end user training
- Bthe building of the disaster recovery environment
- Cthe usage of user acceptance test scripts
- Dthe transactions to use for the tests
How the community answered
(40 responses)- A78% (31)
- B10% (4)
- D13% (5)