MB5-705 · Question #9

MB5-705 Question #9: Real Exam Question with Answer & Explanation

The correct answer is D. During project scoping and planning in the Analysis phase.. See the full explanation below for the reasoning.

Question

Your company is preparing a proposal for a large and complex implementation that will require significant customizations in an enterprise organization. One of the elements that you plan to address is testing and creating a test plan. When is the best time to create a high-level test plan that includes the general standards and procedures that must be followed when conducting software testing and validation?

Options

  • ADuring the beginning of the deployment phase.
  • BAfter design specifications are finalized.
  • CDuring the custom code activity.
  • DDuring project scoping and planning in the Analysis phase.