MB5-705 · Question #9
MB5-705 Question #9: Real Exam Question with Answer & Explanation
The correct answer is D. During project scoping and planning in the Analysis phase.. See the full explanation below for the reasoning.
Question
Your company is preparing a proposal for a large and complex implementation that will require significant customizations in an enterprise organization. One of the elements that you plan to address is testing and creating a test plan. When is the best time to create a high-level test plan that includes the general standards and procedures that must be followed when conducting software testing and validation?
Options
- ADuring the beginning of the deployment phase.
- BAfter design specifications are finalized.
- CDuring the custom code activity.
- DDuring project scoping and planning in the Analysis phase.