nerdexam
Microsoft

MB5-705 · Question #47

MB5-705 Question #47: Real Exam Question with Answer & Explanation

The correct answer is A. Transition of solution to support complete and formal project closure. C. Obtain complete system acceptance and formal project closure. D. Finalize production specification and formal project closure.. See the full explanation below for the reasoning.

Question

You and your team successfully deployed a Microsoft Dynamics solution at the customer site. Both customer and consulting teams are pleased with the Go-live cutover. Post Go-live support is complete. What are the next milestones you need to plan for? Choose the 3 that apply.

Options

  • ATransition of solution to support complete and formal project closure.
  • BCore team training complete and formal project closure.
  • CObtain complete system acceptance and formal project closure.
  • DFinalize production specification and formal project closure.

Community Discussion

No community discussion yet for this question.

Full MB5-705 Practice
You and your team successfully deployed a Microsoft Dynamics... | MB5-705 Q#47 Answer | NerdExam