Question
You and your team successfully deployed a Microsoft Dynamics solution at the customer site. Both customer and consulting teams are pleased with the Go-live cutover. Post Go-live support is complete. What are the next milestones you need to plan for? Choose the 3 that apply.
Options
- ATransition of solution to support complete and formal project closure.
- BCore team training complete and formal project closure.
- CObtain complete system acceptance and formal project closure.
- DFinalize production specification and formal project closure.