MB5-705 · Question #42

The project manager finalized the schedule for the project after the kick-off meeting with the customer. In the weeks following, the team members requested several changes to some planned…

The correct answer is B. Yes, the schedule is a living document. See the full explanation below for the reasoning.

Question

The project manager finalized the schedule for the project after the kick-off meeting with the customer. In the weeks following, the team members requested several changes to some planned activities. Should the project manager adjust the schedule?

Options

  • ANo, after the schedule is finalized it cannot be altered without formal approval of the steering committee.
  • BYes, the schedule is a living document
  • CYes, the schedule can still change after being finalized but only during the Tollgate Review meeting.
  • DNo, only the Business Decision Maker can still change the agreed upon scheduled dates.

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    85% (23)
  • C
    4% (1)
  • D
    4% (1)