You manage a project with a Standard Project Type approach. The Analysis phase is closed and your team is engaged in design activities. The development consultant reports the technical designs are…
The correct answer is B. Acknowledge the good time performance, but do not begin the development activities before all design. See the full explanation below for the reasoning.
Question
You manage a project with a Standard Project Type approach. The Analysis phase is closed and your team is engaged in design activities. The development consultant reports the technical designs are complete and wants to begin the development activities early. What should you do?
Options
- AAllow the development consultant to start earlier than expected with the development activities.
- BAcknowledge the good time performance, but do not begin the development activities before all design
- CStop the development consultant from beginning development early. Use the gained time to make
- DHaving realized a better project time performance than expected you are Determine if the Go-live cutover
How the community answered
(26 responses)- A4% (1)
- B85% (22)
- C4% (1)
- D8% (2)