Question
Your customer experienced quality issues during a previous software implementation. Your customer is concerned with how you are planning to execute the next project. You collaborate with the customer to plan periodically structured, independent reviews similar to the Optimization Offerings to identify insufficient and ineffective policies. This collaboration is an example of:
Options
- AQuality Control events
- BQuality Assurance events
- CScope Verification events
- DOngoing Risk Management events
How the community answered
(36 responses)- A6% (2)
- B78% (28)
- C3% (1)
- D14% (5)