MB5-705 · Question #3

You are determining the contract type for a new engagement. Based on the available diagnostic information, you come to the following conclusions: - There is uncertainty about a majority of the…

The correct answer is B. Time and Material. See the full explanation below for the reasoning.

Question

You are determining the contract type for a new engagement. Based on the available diagnostic information, you come to the following conclusions:

  • There is uncertainty about a majority of the requirements
  • There is a significant gap between a large set of requirements and

your Microsoft Dynamics solution

  • Your project team is not familiar with the customers's industry
  • Your customer is not familiar with implementation projects and

business software. Which contract type should you recommend?

Options

  • AFixed price
  • BTime and Material
  • CFixed Price for Analysis and Design, Estimate for Development and Deployment
  • DEstimate for Analysis and Design, Fixed Price for Development and Deployment

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    84% (26)
  • C
    3% (1)
  • D
    10% (3)