nerdexam
Microsoft

MB5-705 · Question #24

You are concerned that users might not be able to bridge the existing gap between business processes and the business system that was identified. Which actions should you take as a Project Manager…

The correct answer is A. Advise the application consultant to identify this as a risk and to document it in the Project Risk Register. B. Discuss the problem with the customer and advise them to select key users who understand the business. See the full explanation below for the reasoning.

Question

You are concerned that users might not be able to bridge the existing gap between business processes and the business system that was identified. Which actions should you take as a Project Manager to proactively manage this? Choose the 2 that apply.

Options

  • AAdvise the application consultant to identify this as a risk and to document it in the Project Risk Register.
  • BDiscuss the problem with the customer and advise them to select key users who understand the business
  • CAdvise the application consultant to start making Change Requests for these potential issues, and ensure
  • DAdvise the application consultant to identify this as an issue and update the issue list accordingly.

How the community answered

(61 responses)
  • A
    84% (51)
  • C
    10% (6)
  • D
    7% (4)

Community Discussion

No community discussion yet for this question.

Full MB5-705 Practice