MB5-705 · Question #22

MB5-705 Question #22: Real Exam Question with Answer & Explanation

The correct answer is A. A work breakdown structure, including the project scope in measurable components. D. Estimates of the time necessary to deliver these measurable components.. See the full explanation below for the reasoning.

Question

You need to develop a schedule to manage the timeline, resources and activities required to complete the project in the stipulated time. Which elements are necessary to develop this schedule? Choose the 2 that apply.

Options

  • AA work breakdown structure, including the project scope in measurable components.
  • BThe functional Requirements Document, listing all requirements with detailed information.
  • CThe Technical Design Document, describing how gap requirements will be resolved.
  • DEstimates of the time necessary to deliver these measurable components.