You are the project manager for a Microsoft Dynamics implementation. You need to summarize the in-scope and out-of-scope items. Which three items should you include in the summary? (Each correct…
The correct answer is A. business processes B. functional requirements E. integration requirements. See the full explanation below for the reasoning.
Question
You are the project manager for a Microsoft Dynamics implementation. You need to summarize the in-scope and out-of-scope items. Which three items should you include in the summary? (Each correct answer presents part of the solution. Choose three.)
Options
- Abusiness processes
- Bfunctional requirements
- Cproject plan
- Dskills matrix
- Eintegration requirements
- Fproject type
How the community answered
(30 responses)- A80% (24)
- C10% (3)
- D7% (2)
- F3% (1)