MB5-705 · Question #135

You are a project manager. You create a work breakdown structure (WBS). What is the next step when you use the Microsoft Dynamics Sure Step Methodology resource management techniques?

The correct answer is A. Plan material resources that will be needed. See the full explanation below for the reasoning.

Question

You are a project manager. You create a work breakdown structure (WBS). What is the next step when you use the Microsoft Dynamics Sure Step Methodology resource management techniques?

Options

  • APlan material resources that will be needed.
  • BPlan and use the plan-do-check-act cycle.
  • CPlan and collect the project requirements.
  • DPlan and schedule stakeholder project reviews.

How the community answered

(42 responses)
  • A
    74% (31)
  • B
    17% (7)
  • C
    7% (3)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.