After completing the diagnostic assessments, you have the following project data: - There are at least 50 users - One ISV solution is included - Additional business process workflow mapping is…

The correct answer is B. The Standard Project Type D. The Agile Project Type. See the full explanation below for the reasoning.

Question

After completing the diagnostic assessments, you have the following project data:

  • There are at least 50 users
  • One ISV solution is included
  • Additional business process workflow mapping is required
  • An estimate of 250 hours of customization and complex data migration

is needed

  • The implementation is planned for one site.

Which implementation approaches are recommended by Sure Step? Choose the 2 that apply.

Options

  • AThe Rapid Project Type
  • BThe Standard Project Type
  • CThe Enterprise Project Type
  • DThe Agile Project Type

How the community answered

(43 responses)
  • A
    12% (5)
  • B
    72% (31)
  • C
    16% (7)

Community Discussion