Microsoft
MB5-705 · Question #128
During your requirements and process review, you use the questionnaires provided by Sure Step. What is one of the reasons that you use the questionnaire at this stage?
The correct answer is D. to use as a checklist and a reminder of topics to investigate. See the full explanation below for the reasoning.
Question
During your requirements and process review, you use the questionnaires provided by Sure Step. What is one of the reasons that you use the questionnaire at this stage?
Options
- Ato assist in determining the budget of the project
- Bto use as a tool by the partner prior to meeting with the customer
- Cto create detailed process maps
- Dto use as a checklist and a reminder of topics to investigate
How the community answered
(62 responses)- A3% (2)
- B15% (9)
- C6% (4)
- D76% (47)
Community Discussion
No community discussion yet for this question.