You need to put together a RACI matrix that includes a team member who is an employee of the client. Which activity should be assigned to the team member in the RACI matrix?
The correct answer is A. the functions performed on the project. See the full explanation below for the reasoning.
Question
You need to put together a RACI matrix that includes a team member who is an employee of the client. Which activity should be assigned to the team member in the RACI matrix?
Options
- Athe functions performed on the project
- Bwho will review the project work
- Cwho will complete the project work
- Dthe functions performed for the client, external to the project
How the community answered
(34 responses)- A85% (29)
- B3% (1)
- C3% (1)
- D9% (3)