What is the first customer requirement that you should verify before starting an upgrade assessment?
The correct answer is A. Whether the upgrade from the customer's current implementation version to the targeted version of. See the full explanation below for the reasoning.
Question
What is the first customer requirement that you should verify before starting an upgrade assessment?
Options
- AWhether the upgrade from the customer's current implementation version to the targeted version of
- BWhether there are additional business requirements that must be accounted for.
- CWhether customizations were implemented in the current version and how well these are documented.
- DWhether the customer wants a technical or major upgrade.
How the community answered
(34 responses)- A71% (24)
- B3% (1)
- C9% (3)
- D18% (6)