Question
You are a project manager for Contoso Ltd, an e-commerce company. Contoso's Microsoft Dynamics implementation project is in the deployment phase, and you are planning the user acceptance testing. Which action should be the focus of the testing?
Options
- Atesting the performance to ensure the system can handle the predicted peak time transaction volumes
- Btesting that the system supports the company's transaction data
- Ctesting data migration
- Dtesting the end-to-end system to ensure the system supports the company's transactions