MB-920 · Question #114
A company creates a project plan in Dynamics 365 Project Operations. The project plan must allow a project manager to: - Track profitability, - Collaborate on the work to be performed, and…
The correct answer is A. resourcing D. cost E. scope. In Dynamics 365 Project Operations, the three fundamental project derivatives - mirroring the classic project management triangle - are Scope (E), Cost (D), and Resourcing (A). Scope defines what work needs to be done and supports collaboration on deliverables. Cost tracks…
Question
Options
- Aresourcing
- Bschedule updates
- Cinvoicing
- Dcost
- Escope
How the community answered
(54 responses)- A89% (48)
- B4% (2)
- C7% (4)
Explanation
In Dynamics 365 Project Operations, the three fundamental project derivatives - mirroring the classic project management triangle - are Scope (E), Cost (D), and Resourcing (A). Scope defines what work needs to be done and supports collaboration on deliverables. Cost tracks project expenditures and profitability. Resourcing determines which people are allocated to perform project tasks. Together, these three derivatives allow a project manager to track profitability (cost), collaborate on the work to be performed (scope), and allocate people to tasks (resourcing). Schedule updates (B) are a byproduct of managing these derivatives. Invoicing (C) is a financial output downstream of the project, not a core derivative tracked in the project plan itself.
Topics
Community Discussion
No community discussion yet for this question.