MB-920 · Question #115
A company is implementing Dynamics 365 Project Operations for services operations. The company needs to estimate the full-time resources required to complete different tasks for a new project. You nee
The correct answer is C. work breakdown structure (WBS). Create a work breakdown structure (WBS) A project schedule communicates what work must be completed, which resources do the work, and the timeframe in which the work must be completed. The schedule reflects all the work associated with delivering the project on time. In Dynamics
Question
Options
- Aproject stages
- Bscheduling modes
- Cwork breakdown structure (WBS)
- Dresource utilization
- Ebooking allocation method
How the community answered
(22 responses)- A5% (1)
- C91% (20)
- D5% (1)
Explanation
Create a work breakdown structure (WBS) A project schedule communicates what work must be completed, which resources do the work, and the timeframe in which the work must be completed. The schedule reflects all the work associated with delivering the project on time. In Dynamics 365 Project Operations, you create a project schedule by: Breaking down the work into manageable tasks. Estimating the time that is required to do each task. Setting task dependencies. Setting task durations. Estimating the generic resources that complete the tasks. The project schedule is created on the Schedule tab on the Project page. https://learn.microsoft.com/en-us/dynamics365/project-operations/project-management/create-