MB-700 · Question #169

A Dynamics 365 user is enrolled in the FastTrack program. The user begins the Success by Design framework and is in the first phase of workshops. You need to plan the subsequent phases. What are the…

The correct answer is A. Prepare B. Implement D. Operate. The FastTrack Success by Design framework has four phases - Initiate, Implement, Prepare, and Operate - so after completing the first phase (Initiate), the three remaining phases are Implement, Prepare, and Operate.

Manage implementations

Question

A Dynamics 365 user is enrolled in the FastTrack program. The user begins the Success by Design framework and is in the first phase of workshops. You need to plan the subsequent phases. What are the three remaining phases? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

Options

  • APrepare
  • BImplement
  • CInitiate
  • DOperate
  • ESolution Blueprint Review

How the community answered

(15 responses)
  • A
    93% (14)
  • E
    7% (1)

Why each option

The FastTrack Success by Design framework has four phases - Initiate, Implement, Prepare, and Operate - so after completing the first phase (Initiate), the three remaining phases are Implement, Prepare, and Operate.

APrepareCorrect

Prepare is the third phase of the Success by Design framework, occurring after Implement, and focuses on go-live readiness activities such as environment preparation, cutover planning, and training.

BImplementCorrect

Implement is the second phase of the Success by Design framework, following Initiate, and covers solution design, development, testing, and iterative workshops during the build phase.

CInitiate

Initiate is the first phase of the Success by Design framework - the phase the user is currently completing - so it cannot be one of the remaining subsequent phases.

DOperateCorrect

Operate is the fourth and final phase of the Success by Design framework, occurring after go-live, and focuses on stabilization, hypercare support, and continuous improvement of the solution.

ESolution Blueprint Review

Solution Blueprint Review is a specific governance review workshop that occurs within the early phases of the framework, not a standalone named phase in the Success by Design lifecycle.

Concept tested: FastTrack Success by Design framework phases

Source: https://learn.microsoft.com/en-us/dynamics365/fasttrack/success-by-design

Topics

#Dynamics 365 FastTrack#Success by Design#Project phases#Implementation planning