MB-335 · Question #96

You are the lead product design engineer at a plastics manufacturing company. You implement a new process that uses a single tool to produce three finished goods at the same time. You need to set up…

The correct answer is A. Create item number for planning item and the associated formula. B. Specify each of the finished good items as co-products. D. Assign co-products to the formula. You've hit your limit · resets 4am (America/New_York)

Configure products

Question

You are the lead product design engineer at a plastics manufacturing company. You implement a new process that uses a single tool to produce three finished goods at the same time. You need to set up the planning item number and formula to correctly to manufacture the three items. Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

Options

  • ACreate item number for planning item and the associated formula.
  • BSpecify each of the finished good items as co-products.
  • CAdd minimum and maximum quantities on formula.
  • DAssign co-products to the formula.
  • EAdd a coverage group to the formula.

How the community answered

(28 responses)
  • A
    71% (20)
  • C
    11% (3)
  • E
    18% (5)

Explanation

You've hit your limit · resets 4am (America/New_York)

Topics

#planning item#formula#co-products#co-production