MB-335 · Question #91
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup: - The setup uses a Lean schedule group with a…
The correct answer is D. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 0.0167. Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing…
Question
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup:
- The setup uses a Lean schedule group with a throughput ratio = 2.
- The process activity tied to production flow has the following
runtime activity times: time = 3 min, per quantity = 1.
- The work cell capacity has a model type of Throughput and an average
throughput quantity of 60 per a capacity period of standard workday (8 hour day).
- The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?
Options
- ACreate a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.
- BCreate a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 1.
- CCreate a route with a runtime = 10, a process quantity = 6, and the operation's hours/time = 1.
- DCreate a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 0.0167
How the community answered
(35 responses)- A3% (1)
- B9% (3)
- C17% (6)
- D71% (25)
Explanation
Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing- routes/create-operations-relations https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean- schedule-groups#associate-product
Topics