MB-335 · Question #72

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup: - The setup uses a Lean schedule group with a…

The correct answer is B. Create a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 0.0167. Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing…

Implement production methods

Question

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup:

  • The setup uses a Lean schedule group with a throughput ratio = 2.
  • The process activity tied to production flow has the following

runtime activity times: time = 3 min, per quantity = 1.

  • The work cell capacity has a model type of Throughput and an average

throughput quantity of 60 per a capacity period of standard workday (8 hour day).

  • The throughput is 10 per hour.

You need to set up a Discrete operation to mirror the item's production flow activity. What should you do?

Options

  • ACreate a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 1.
  • BCreate a route with a runtime = 6, a process quantity = 1, and the operation's hours/time = 0.0167
  • CCreate a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 0.0167
  • DCreate a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 0.0167

How the community answered

(15 responses)
  • A
    7% (1)
  • B
    67% (10)
  • C
    7% (1)
  • D
    20% (3)

Explanation

Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing- routes/create-operations-relations https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean- schedule-groups#associate-product

Topics

#lean manufacturing#discrete manufacturing#throughput calculation#route operations