MB-335 · Question #218

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might…

The correct answer is A. Yes. You've hit your limit · resets 4am (America/New_York)

Implement production methods

Question

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution. After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen. A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service. You need to create a subcontracting activity for the painting service. Solution:

  • Create a vendor resource and work cell for outsourced painting; add the vendor resource to the

work cell.

  • Create a production flow process activity using the painting work cell and the service item for

picking.

  • When the service is required, create a purchase order to the subcontracting vendor and add a

line for the service item and the vendor price. Does the solution meet the goal?

Options

  • AYes
  • BNo

How the community answered

(19 responses)
  • A
    74% (14)
  • B
    26% (5)

Explanation

You've hit your limit · resets 4am (America/New_York)

Topics

#Lean manufacturing#subcontracting#production flow#service items